Packaging Details: | Packing:carton About 40000m2/20'GP Main tee:25pcs, Long cross tee:50pcs, Short cross tee:75pcs, Wall angle: 50pcs |
Delivery Detail: | Within 2 weeks after T/T deposit or L/C issued(According to the arrangemt in factory. |
Installation steps:
1). Determine the requirment ceiling level,mark the position and fix wall angle on the wall.
2). Hang main tee with T-bar suspension hook.
3). Insert cross tee to the main tee.
4). Cross tee adjacent to wall angle light fittings
5). Adjust the levels and alignments throughout the entire grid system accurately
6). Install PVC gypsum ceiling tile or other ceiling panel.