None in such quantities that shall interfere with the reception, regasification, transportation of LNG or the use of LNG as Natural Gas.
SOLIDS AND OTHER IMPURITIES:
TOTAL SULPHUR: 28.0 mg/Nm3 MAXIMUM
HYDROGEN SULFIDE: 4.80 MG/Nm3 MAXIMUM
C IMPURITIES WITHIN THE FOLLOWING RANGES:
NITROGEN: 1.00 MOL % MAXIMUM
PENTANES AND HEAVIER: 0.10 MOL % MAXIMUM
BUTANES AND HEAVIER: 2.00 MOL % MAXIMUM
METHANE: 86.00 MOL % MINIMUM
B HYDROCARBON CPMPOSITION AND NITROGEN CONTENT WITHIN THE FOLLOWING RANGES:
MAXIMUM: 1170 Btu/SCF
MINIMUM: 1050 Btu/SCF
A GROSS HEATING VALUE (VOLUME BASEAD)
LNG QUALITITY & SPECIFICATIONS
? Shipment commences upon completion and verification of all documents,
? Seller issues PB to activate buyer's Letter of Credit or other acceptable means of payment as Agreed on Contract.
? Buyer's bank issues Non-Operative Letter of Credit or other acceptable means of payments to Seller.
? Seller issue to buyer the Full POP against POF
? Seller issues original contract (Hard Copies) for final signatory, both parties exchange Hard Copies of Contract via Courier Service.
? Buyer signs Draft Contract and return to Seller.
? Seller issues Draft Contract with a Partial POP via Bank Swift.
? Buyer issues ICPO with soft probe authorization + NCNDA + IMFPA
? Original Seller / Seller mandate with Proof issues a Soft Corporate offer on their Letter Head.
Procedure Guideline:
? Past performance (sanitised) to be provided alongwith draft contract
? Further Confirmations are Strictly subject to receipt of Said Proof which has to be Fully True.
? The Quality and Quantity Inspection will be made by an Independent Surveyor at Loading and Unloading Terminals at Seller expenses for every shipment.
? The payment procedure to be mutually agreed between BUYER and SELLER in the SPA;
? The duration of the SPA to be mutually agreed between BUYER and SELLER in the SPA. The MINIMUM will be sixty (60) months or five(5) years;
? Commencement of deliveries will be 30-45 days upon execution of the SPA;
? The Delivery Terminal will be as per BUYERs advice within a range of regasification terminals to include but not limited to CANAPORT LNG (in CANADA) and any regasification terminal in SPAIN, FRANCE or ITALY. All deliveries will be on a FOB BASIS ( as INCOTERMS 2000);
? The loading terminal will be at sellers option, any liquefaction plant; provided that the quality and composition of the LNG complies with the SPECIFICATION as per ANNEX 1 and is notified well in advance on the same;
Annual fixed price per MT (FOB/CIF) Or SPOT (FOB/CIF) This Purchase Price will be revised on yearly basis according to an indexation mechanism to be agreed upon by the Parties in the Definitive Agreements;
;
SALE AND PURCHASE OF LNG
LNG on Annual CONTRACT basis/ SPOT.CIF/FOB
Delivery Time: | 45-60 Days |
Package: | BULK |
Minimum Order Quantity: | 100,000 Metric Ton |
Payment Terms: | L/C |
Port: | ROTTERDOM |
Fob Price: | US$350-420ROTTERDOM |
Type: | LNG |
Brand Name: | LNG |
Place of Origin: | Russian Federation |
lng plant process LNG Liquefaction Plant After compression, the feed gas is processed by dehydration and heavy hydrocarbon separation units. Please see the attached PFD. LNG plant process description is detailed as follows: Feed gas compress unit After measuring, the feed gas ...
Come From Peiyang Chemical Equipment Co., Ltd.
LNG Plant Process Process of LNG Liquefaction Plant After compression, the feed gas is processed by dehydration and heavy hydrocarbon separation units. Please see the attached PFD. Process description is detailed as follows: Feed gas compress unit After measuring, the feed gas ...
Come From Peiyang Chemical Equipment Co., Ltd.
Product Description Developed for the industrial gas industry to indicate cryogenic tank liquid contents. It has 6-inch(152mm) or 4-inch(100mm) indicator and is designed for tank level, by providing a direct acting differential pressure indication of cryogenic liquids such as ...
Come From Dongying Lake Petroleum Technology Co.,